Live Now:   

Army construct collapsed foot-over bridge in 5 days, hand it over to Delhi govt

New Delhi: The Army on Friday handed over the newly-built Bailey foot overbridge outside the main Commonwealth Games venue Jawaharlal Nehru stadium to the Delhi government, six days after it was tasked to construct it.

The Army was approached by the Delhi Government after a 95-metre-long under-construction foot overbridge came crashing down on September 21, injuring 27 people and causing a major embarrassment to the country.

The Army engineers had started work on the bridge on Saturday and completed its construction on Wednesday.

The hanging bridge, which was intended to be a showpiece, was built by a private firm for Delhi Government’s Public Works Department along with another adjacent bridge at a cost of Rs 10.5 crore to connect the parking lot of the stadium with other side of the street in Lodhi Road in south Delhi.

In pic: In less than a week, Army’s ‘Madras Sappers’ have built 95-metre-long Bailey bridge near JLN Stadium, main venue of Commonwealth Games.

An army engineering regiment with nearly 1,000 men was deployed to construct the Bailey bridge which is a portable pre-fabricated bridge designed for use by military units.

The Delhi Government official said the PWD has completed construction of the second foot overbridge, adjacent to the collapsed bridge.

Leave a Reply

The latest researches: High Quality European Replica, Top Style Watches, Replica Watches, 5 Stars Watches, Top Brands Watches, Watches For Sale, Luxury Watches, AAA Quality Watches, AAA Grade Watches, High Quality Replica Watches, High Quality Watches, Luxury Replica Watches, AAA Replica Watches, Replica Watches For Sale, Watches Online, Watches Shop, Watches Store, Watches OTC, The Best Watches, The Best Replica Watches